Road occupancy permits and damage deposits in Guelph, Ontario

Guelph, Ontario, Canada

Get a Guelph road occupancy permit before using any city right-of-way, including the road, boulevard, sidewalk or multi-use trail. Choose the application for utility, site servicing, capital or miscellaneous work.

Key information

Get a Guelph road occupancy permit before using any city right-of-way, including the road, boulevard, sidewalk or multi-use trail. Choose the application for utility, site servicing, capital or miscellaneous work.

On this page

Prepare the correct submission at a glance

Prepare the correct submission
  1. Select the work category

    Select the work category. Site servicing must already have approval through the relevant site-plan, building, mechanical or other process. Special events use the separate special-event process.

  2. Include a traffic-control plan when pedestrians or traffic are affected

    Include a traffic-control plan when pedestrians or traffic are affected. It must meet Ontario Traffic Manual Book 7 temporary-conditions requirements. Allow the required notification lead time before the start date.

  3. Download and save the forms

    Download and save the forms, open in Adobe Acrobat Reader as recommended, and email the complete package to rop@guelph.ca for review.

Sources: Street occupancy permits

General application lead times

Application lead time by traffic effect. Values match the table below.
  • No traffic impact5 working days
  • Local or collector-road traffic impact10 working days
  • Arterial-road traffic impact20 working days
General application lead times
Traffic effectWorking days before start
No traffic impact5
Local or collector-road traffic impact10
Arterial-road traffic impact20

Sources: Street occupancy permits

Prepare the correct submission

  1. Select the work category. Site servicing must already have approval through the relevant site-plan, building, mechanical or other process. Special events use the separate special-event process.
  2. Include a traffic-control plan when pedestrians or traffic are affected. It must meet Ontario Traffic Manual Book 7 temporary-conditions requirements. Allow the required notification lead time before the start date.
  3. Download and save the forms, open in Adobe Acrobat Reader as recommended, and email the complete package to rop@guelph.ca for review.

Sources: Street occupancy permits

Miscellaneous work damage-deposit examples

Miscellaneous work damage-deposit examples
WorkListed estimate
Temporary containers, equipment operation or temporary construction fencingNone for the listed non-invasive category
Material placement, deliveries or installed scaffolding$500
Boulevard landscaping, cranes, driveways or digging$1,000
Equipment across curbs/sidewalks, boreholes or work near a city treeSpecial assessment

Sources: Street occupancy permits

Fees and approval limits

The source lists a $120 site-servicing fee, typically taken from an existing project deposit, and a $120 miscellaneous fee. Utility works have no permit fee. Damage deposits can apply in addition to the fee.

An existing site-servicing approval deposit can remove the need for another damage deposit. Submit the project details so staff can establish what applies; the category examples do not replace an individual assessment.

The page introduces three permit types but also identifies a separate capital-project route for city-hired contractors. This guide preserves all four published routes rather than omitting capital work.

Sources: Street occupancy permits

Questions and answers

Does a sidewalk occupation need a permit?

Yes. The right-of-way includes sidewalks and multi-use trails as well as the road and boulevard.

Source: Street occupancy permits

Are disposal bins part of miscellaneous work?

Yes. Containers, bins and mobile storage are listed examples.

Source: Street occupancy permits

What is the usual fee for miscellaneous work?

$120, with any required damage deposit additional.

Source: Street occupancy permits

Do utility works have a permit fee?

The source says no permit fee for utility works.

Source: Street occupancy permits

Can I choose tomorrow as a start date?

General lead times are 5,10 or 20 working days depending on traffic impacts.

Source: Street occupancy permits

Does pedestrian impact need a control plan?

Yes. A proposed plan is required for effects on pedestrians or traffic.

Source: Street occupancy permits

What standard applies to the traffic plan?

Ontario Traffic Manual Book 7 for temporary conditions.

Source: Street occupancy permits

Do site-servicing works need another project approval first?

Yes. The city says they must already be approved through the relevant project process.

Source: Street occupancy permits

Can an existing deposit cover site servicing?

Where a deposit already exists in the approval process, a new damage deposit is not required with that application.

Source: Street occupancy permits

Where is the completed package sent?

Email rop@guelph.ca.

Source: Street occupancy permits

Sources: Street occupancy permits